Dept. of Trans. PROGRESS Serial No. Contract No. 10-113-14-24 08-452204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-RIV-15-40.0/40.7 Federal Project: STPL-5104(32) N-5104(32) Progress payment No. 29 Payment period ending: 04-20-10 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,854,932.84 7,117.50 2.a. Extra Work 806,374.91 12,308.32 b. Adjustment Comp. -28,904.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,632,403.27 19,425.82 5. Mobilization 1,106,920.00 0.00 6. Total Work Completed 13,739,323.27 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,739,323.27 19,425.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,425.82