Dept. of Trans. PROGRESS Serial No. Contract No. 10-299-16-16 08-456004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 41% 08-RIV-10-41.3/44.6 Federal Project: ARRA-103(127) L-103(127) ACIM-103(127) Progress payment No. 09 Payment period ending: 10-20-10 SEMA CONSTRUCTION INC 6 ORCHARD SUITE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,617,979.51 700,825.79 2.a. Extra Work 42,246.63 -693.79 b. Adjustment Comp. 3. Materials on Hand 122,037.90 -78,970.00 4. Earned Subject to Retention 9,782,264.04 621,162.00 5. Mobilization 2,090,000.00 0.00 6. Total Work Completed 11,750,226.14 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,872,264.04 621,162.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 621,162.00