Dept. of Trans. PROGRESS Serial No. Contract No. 07-360-15-41 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 37% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 10 Payment period ending: 12-20-07 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,637,969.14 671,377.01 2.a. Extra Work 49,058.07 14,569.59 b. Adjustment Comp. -12,263.42 -6,826.25 3. Materials on Hand 85,039.72 -11,904.29 4. Earned Subject to Retention 6,759,803.51 667,216.06 5. Mobilization 560,125.00 28,006.25 6. Total Work Completed 7,234,888.79 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,314,928.51 690,222.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 690,222.31