Dept. of Trans. PROGRESS Serial No. Contract No. 08-026-11-47 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 40% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 11 Payment period ending: 01-18-08 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,984,728.03 346,758.89 2.a. Extra Work 55,140.72 6,082.65 b. Adjustment Comp. -12,263.42 0.00 3. Materials on Hand 163,873.66 78,833.94 4. Earned Subject to Retention 7,191,478.99 431,675.48 5. Mobilization 560,125.00 0.00 6. Total Work Completed 7,587,730.33 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,746,603.99 431,675.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 431,675.48