Dept. of Trans. PROGRESS Serial No. Contract No. 08-057-12-48 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 43% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 12 Payment period ending: 02-20-08 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,396,984.89 412,256.86 2.a. Extra Work 75,591.63 20,450.91 b. Adjustment Comp. -10,436.90 1,826.52 3. Materials on Hand 155,208.74 -8,664.92 4. Earned Subject to Retention 7,617,348.36 425,869.37 5. Mobilization 560,125.00 0.00 6. Total Work Completed 8,022,264.62 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,172,473.36 425,869.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 425,869.37