Dept. of Trans. PROGRESS Serial No. Contract No. 08-086-09-28 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 47% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 13 Payment period ending: 03-20-08 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,186,589.29 789,604.40 2.a. Extra Work 89,481.82 13,890.19 b. Adjustment Comp. -7,390.17 3,046.73 3. Materials on Hand 172,139.54 16,930.80 4. Earned Subject to Retention 8,440,820.48 823,472.12 5. Mobilization 560,125.00 0.00 6. Total Work Completed 8,828,805.94 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,995,945.48 823,472.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 823,472.12