Dept. of Trans. PROGRESS Serial No. Contract No. 08-206-14-20 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 63% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 17 Payment period ending: 07-18-08 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,974,879.80 726,776.16 2.a. Extra Work 159,525.33 2,527.62 b. Adjustment Comp. 5,609.83 0.00 3. Materials on Hand 33,917.56 -85,301.00 4. Earned Subject to Retention 10,173,932.52 644,002.78 5. Mobilization 560,125.00 0.00 6. Total Work Completed 10,700,139.96 7. Deductions -15,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,719,057.52 634,002.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 634,002.78