Dept. of Trans. PROGRESS Serial No. Contract No. 08-298-13-17 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 76% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 20 Payment period ending: 10-20-08 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,922,148.13 305,570.50 2.a. Extra Work 162,128.89 2,603.56 b. Adjustment Comp. 74,755.61 69,145.78 3. Materials on Hand 29,917.56 -60,145.78 4. Earned Subject to Retention 11,188,950.19 317,174.06 5. Mobilization 560,125.00 0.00 6. Total Work Completed 11,719,157.63 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,734,075.19 317,174.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 317,174.06