Dept. of Trans. PROGRESS Serial No. Contract No. 08-330-08-31 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 80% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 21 Payment period ending: 11-20-08 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,481,699.36 559,551.23 2.a. Extra Work 173,432.58 11,303.69 b. Adjustment Comp. 65,176.71 -9,578.90 3. Materials on Hand 9,499.07 -20,418.49 4. Earned Subject to Retention 11,729,807.72 540,857.53 5. Mobilization 560,125.00 0.00 6. Total Work Completed 12,280,433.65 7. Deductions -5,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,284,932.72 550,857.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 550,857.53