Dept. of Trans. PROGRESS Serial No. Contract No. 09-057-13-09 08-456614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 92% 08-RIV-91-R0.6/R1.2 Federal Project: HP21-6054(49) LN-6054(49) Progress payment No. 24 Payment period ending: 02-20-09 SEMA CONSTRUCTION INC 6 ORCHARD STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,581,708.53 222,982.22 2.a. Extra Work 186,488.00 0.00 b. Adjustment Comp. 40,899.32 -7,367.25 3. Materials on Hand 4. Earned Subject to Retention 12,809,095.85 215,614.97 5. Mobilization 560,125.00 0.00 6. Total Work Completed 13,369,220.85 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,364,220.85 215,614.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 215,614.97