Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-051-09-56 08-472224 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-15-3.8/12.8 ACIM-155(155) 110-(155) Progress payment No. 020 Payment period ending: 11-21-14 GRIFFITH/COFFMAN JOINT VENTURE 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 71,702,064.41 4,498,309.95 2. a. Extra Work 1,747,260.47 529,480.06 b. Adustment Comp. 2,298,409.99 2,272,209.99 3. Materials on Hand 4. Earned Subject to Retention 75,747,734.87 7,300,000.00 5. Mobilization 7,700,903.96 0.00 6. Total Work Completed 83,448,638.83 7. Deductions -0.01 -0.01 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 83,448,638.82 7,299,999.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,299,999.99