Dept. of Trans. PROGRESS Serial No. Contract No. 10-207-14-18 08-472304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-RIV-10-R0.0/R8.2 Federal Project: ACIM-102(254) Progress payment No. 18 Payment period ending: 07-20-10 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,434,924.01 1,812,953.41 2.a. Extra Work 590,025.63 77,252.13 b. Adjustment Comp. 1,109,321.14 -58,385.01 3. Materials on Hand 193,897.78 -718.41 4. Earned Subject to Retention 28,328,168.56 1,831,102.12 5. Mobilization 3,880,000.00 0.00 6. Total Work Completed 32,014,270.78 7. Deductions -8,590.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,199,578.56 1,831,102.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,831,102.12