Dept. of Trans. PROGRESS Serial No. Contract No. 10-358-08-54 08-472304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-RIV-10-R0.0/R8.2 Federal Project: ACIM-102(254) Progress payment No. 24 Payment period ending: 12-20-10 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,781,765.00 1,358,620.56 2.a. Extra Work 809,789.13 28,406.46 b. Adjustment Comp. 1,480,249.69 14,295.60 3. Materials on Hand 181,809.03 35,690.00 4. Earned Subject to Retention 37,253,612.85 1,437,012.62 5. Mobilization 3,880,000.00 0.00 6. Total Work Completed 40,951,803.82 7. Deductions -8,590.00 4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,125,022.85 1,441,012.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,441,012.62