Dept. of Trans. PROGRESS Serial No. Contract No. 00-270-08-13 08-472404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 34% 08-RIV-74-8.6/11.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-20-00 J MC LOUGHLIN ENGINEERING CO INC 10722 ARROW RTE SUITE 716 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 192,466.91 68,754.66 2.a. Extra Work 11,341.75 3,219.71 b. Adjustment Comp. 3. Materials on Hand 14,891.45 -12,257.27 4. Earned Subject to Retention 218,700.11 59,717.10 5. Mobilization 6. Total Work Completed 203,808.66 7. Deductions 8. a.Contract Retentions -11,528.00 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 207,172.11 59,717.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,717.10