Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-032-14-19 08-474204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-10-30.9/31.9 Federal Project: ACIM-010-2(251) Progress payment No. 21 Payment period ending: 01-20-06 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 895,627.86 0.00 2.a. Extra Work 65,790.69 0.00 b. Adjustment Comp. -39,000.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 922,417.89 0.00 5. Mobilization 78,000.00 0.00 6. Total Work Completed 1,000,417.89 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,000,417.89 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00