Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-042-14-04 08-476104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-R115.3/R119.0 Federal Project: NONE Progress payment No. 16 Payment period ending: 11-02-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,932,684.08 -52,460.00 2.a. Extra Work 884,093.54 0.00 b. Adjustment Comp. 885,859.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,702,637.11 -52,460.00 5. Mobilization 352,757.00 0.00 6. Total Work Completed 8,055,394.11 7. Deductions 8. a.Contract Retentions -348,864.54 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 348,864.54 0.00 9. Total pay to Contractor 8,055,394.11 -52,460.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -52,460.00