Dept. of Trans. PROGRESS Serial No. Contract No. 21-145-07-34 08-476424 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 24% Location: Federal Project: 08-SBD-215-7.0/17.8 NONE Progress payment No. 004 Payment period ending: 05-20-21 ALDRIDGE ELECTRIC INC 844 E ROCKLAND RD LIBERTYVILLE IL 60048 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 616,980.10 308,561.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 238,301.66 125,306.56 4. Earned Subject to Retention 855,281.76 433,867.76 5. Mobilization 393,750.00 131,250.00 6. Total Work Completed 1,010,730.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,249,031.76 565,117.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 565,117.76