Dept. of Trans. PROGRESS Serial No. Contract No. 11-207-16-00 08-478604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 30% 08-RIV-86-R16.0/R16.7 Federal Project: ACNH-P086(72) Progress payment No. 04 Payment period ending: 07-20-11 SEMA CONSTRUCTION INC 6 ORCHARD SUITE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 642,806.64 253,777.16 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -50,000.00 4. Earned Subject to Retention 642,806.64 203,777.16 5. Mobilization 228,813.84 76,271.28 6. Total Work Completed 871,620.48 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 871,620.48 280,048.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 280,048.44