Dept. of Trans. PROGRESS Serial No. Contract No. 12-026-09-52 08-478604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 92% 08-RIV-86-R16.0/R16.7 Federal Project: ACNH-P086(72) Progress payment No. 10 Payment period ending: 01-19-12 SEMA CONSTRUCTION INC 6 ORCHARD SUITE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,310,312.30 596,284.40 2.a. Extra Work 12,522.53 0.00 b. Adjustment Comp. 3. Materials on Hand 66,493.98 -88,753.28 4. Earned Subject to Retention 4,389,328.81 507,531.12 5. Mobilization 305,085.12 0.00 6. Total Work Completed 4,627,919.95 7. Deductions -2,499.30 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,691,914.63 507,531.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 507,531.12