Dept. of Trans. PROGRESS Serial No. Contract No. 04-026-12-58 08-483744 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 33% 08-SBD-40-R131.5/R154.6 Federal Project: ACIM-040-2(49) ACIM-040-2(49) Progress payment No. 08 Payment period ending: 01-20-04 YEAGER SKANSKA INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 02072 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,538.00 74,878.00 2.a. Extra Work 6,462.05 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 213,000.05 74,878.00 5. Mobilization 6. Total Work Completed 213,000.05 7. Deductions 8. a.Contract Retentions -21,300.01 -7,487.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 191,700.04 67,390.20 10. Reduction Amt to Escrow 11. Payment to Escrow 21,300.00 12. Net Pymt. this Estimate 67,390.20