Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-215-10-35 08-483764 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-40-R106.5/R108.0 Federal Project: ACIM-040-2(51) ACIM-040-2(51) Progress payment No. 30 Payment period ending: 05-25-06 KIEWIT PACIFIC CO 3888 E BROADWAY RD PHOENIX AZ 85040 Escrow No. 02149 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,568,424.70 72,202.00 2.a. Extra Work 422,335.98 103,327.04 b. Adjustment Comp. 253,920.97 -8,454.31 3. Materials on Hand 4. Earned Subject to Retention 6,244,681.65 167,074.73 5. Mobilization 465,000.00 0.00 6. Total Work Completed 6,709,681.65 7. Deductions -76,766.43 14,400.00 8. a.Contract Retentions -303,880.35 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 303,880.35 303,880.35 9. Total pay to Contractor 6,632,915.22 485,355.08 10. Reduction Amt to Escrow -303,880.00 -303,880.00 11. Payment to Escrow 303,880.00 12. Net Pymt. this Estimate 181,475.08