Dept. of Trans. PROGRESS Serial No. Contract No. 03-175-13-16 08-493504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 11% 08-SBD-15-41.1/41.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-17-03 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 102,739.45 67,579.45 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 102,739.45 67,579.45 5. Mobilization 28,500.00 9,500.00 6. Total Work Completed 131,239.45 7. Deductions 8. a.Contract Retentions -10,273.95 -6,757.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 120,965.50 70,321.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,321.50