Dept. of Trans. PROGRESS Serial No. Contract No. 05-207-09-01 08-493504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 68% 08-SBD-15-41.1/41.7 Federal Project: NONE Progress payment No. 27 Payment period ending: 07-20-05 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02151 Total Estimate This Estimate 1. Contract Itms Without Mobil. 630,161.50 4,667.60 2.a. Extra Work 6,124.85 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 636,286.35 4,667.60 5. Mobilization 38,000.00 0.00 6. Total Work Completed 674,286.35 7. Deductions 8. a.Contract Retentions -31,814.32 -233.38 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 642,472.03 4,434.22 10. Reduction Amt to Escrow 11. Payment to Escrow 31,580.00 12. Net Pymt. this Estimate 4,434.22