Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-16-31 08-493504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-15-41.1/41.7 Federal Project: NONE Progress payment No. 42 Payment period ending: 10-19-06 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02151 Total Estimate This Estimate 1. Contract Itms Without Mobil. 695,891.00 -6,165.00 2.a. Extra Work 28,645.26 20,907.57 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 724,536.26 14,742.57 5. Mobilization 38,000.00 0.00 6. Total Work Completed 762,536.26 7. Deductions -7,000.00 -7,000.00 8. a.Contract Retentions -36,226.81 -737.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 719,309.45 7,005.44 10. Reduction Amt to Escrow 11. Payment to Escrow 36,220.00 12. Net Pymt. this Estimate 7,005.44