Dept. of Trans. PROGRESS Serial No. Contract No. 08-115-10-56 08-495204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 18% 08-RIV-15-8.2/23.9 Federal Project: ACIM-015-5(150) Progress payment No. 05 Payment period ending: 04-18-08 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,492,782.78 1,758,636.96 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -78,667.80 4. Earned Subject to Retention 2,492,782.78 1,679,969.16 5. Mobilization 79,610.00 37,710.00 6. Total Work Completed 2,572,392.78 7. Deductions -25.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,572,367.78 1,717,679.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,717,679.16