Dept. of Trans. PROGRESS Serial No. Contract No. 05-207-16-36 08-498004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 47% 08-SBD-210-R8.3/R15.1 Federal Project: STPL-6208(4) Progress payment No. 21 Payment period ending: 06-20-05 BELAIRE WEST LANDSCAPE INC P O BOX 6270 BUENA PARK CA 90622 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,258,372.00 10,527.80 2.a. Extra Work 397,492.39 0.00 b. Adjustment Comp. 59,100.04 -4,637.12 3. Materials on Hand 4. Earned Subject to Retention 3,714,964.43 5,890.68 5. Mobilization 50,000.00 0.00 6. Total Work Completed 3,764,964.43 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions -185,748.22 -294.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,574,216.21 596.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 596.15