Dept. of Trans. PROGRESS Serial No. Contract No. 07-144-13-03 08-498504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 48% 08-SBD-38-2.9/4.3 Federal Project: ACST-P038(16) PH-P038(16) Progress payment No. 02 Payment period ending: 05-20-07 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 431,617.63 207,256.63 2.a. Extra Work 9,000.00 9,000.00 b. Adjustment Comp. 2,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 443,117.63 216,256.63 5. Mobilization 62,160.40 13,086.40 6. Total Work Completed 505,278.03 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 505,278.03 229,343.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,343.03