Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-09-32 09-0AA034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 100% 09-INY-6-0.1/ .0 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-10 SOLEX ELECTRONICS INC 19481 HARBORGATE WAY TORRANCE CA 90501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,393.44 23,393.44 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 23,393.44 23,393.44 5. Mobilization 6. Total Work Completed 23,393.44 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,393.44 23,393.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,393.44