Dept. of Trans. PROGRESS Serial No. Contract No. 22-230-10-33 09-213404 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 27% Location: Federal Project: 09-INY-395-29.2/41.8 ACNH-P395(348) Progress payment No. 007 Payment period ending: 08-18-22 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,445,722.29 1,341,424.39 2. a. Extra Work 119,361.14 38,485.53 b. Adustment Comp. -61,314.30 0.00 3. Materials on Hand 71,767.42 0.00 4. Earned Subject to Retention 6,575,536.55 1,379,909.92 5. Mobilization 4,933,065.59 1,644,355.20 6. Total Work Completed 11,436,834.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,508,602.14 3,024,265.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,024,265.12