Dept. of Trans. PROGRESS Serial No. Contract No. 22-325-09-33 09-213404 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 39% Location: Federal Project: 09-INY-395-29.2/41.8 ACNH-P395(348) Progress payment No. 010 Payment period ending: 11-18-22 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,460,955.15 1,392,678.50 2. a. Extra Work 162,641.62 20,568.30 b. Adustment Comp. -61,314.30 0.00 3. Materials on Hand 145,167.16 19,666.31 4. Earned Subject to Retention 10,707,449.63 1,432,913.11 5. Mobilization 4,933,065.59 0.00 6. Total Work Completed 15,495,348.06 7. Deductions -1,200.00 -1,200.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,639,315.22 1,431,713.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,431,713.11