Dept. of Trans. PROGRESS Serial No. Contract No. 21-201-14-44 09-213414 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 43% Location: Federal Project: 09-INY-395-29.9/41.8 ACNH-P395(346) Progress payment No. 003 Payment period ending: 07-20-21 ALCORN FENCE COMPANY 9901 GLENOAKS BLVD SUN VALLEY CA 91352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 442,924.00 222,847.15 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 442,924.00 222,847.15 5. Mobilization 38,000.00 8,000.00 6. Total Work Completed 480,924.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 480,924.00 230,847.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,847.15