Dept. of Trans. PROGRESS Serial No. Contract No. 09-164-09-26 09-2144U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 41% 09-INY-395-65.0/76.1 Federal Project: NONE Progress payment No. 10 Payment period ending: 06-12-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 02414 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,305,040.79 1,073,821.25 2.a. Extra Work 280,202.41 807.36 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,585,243.20 1,074,628.61 5. Mobilization 3,353,875.25 0.00 6. Total Work Completed 13,939,118.45 7. Deductions 8. a.Contract Retentions -714,961.21 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,224,157.24 1,074,628.61 10. Reduction Amt to Escrow 11. Payment to Escrow 714,960.00 12. Net Pymt. this Estimate 1,074,628.61