Dept. of Trans. PROGRESS Serial No. Contract No. 10-294-08-17 09-2144U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 99% 09-INY-395-65.0/76.1 Federal Project: NONE Progress payment No. 26 Payment period ending: 10-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 02414 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,559,899.65 479,813.87 2.a. Extra Work 1,328,084.70 19,666.94 b. Adjustment Comp. -450,004.38 0.00 3. Materials on Hand 4. Earned Subject to Retention 35,437,979.97 499,480.81 5. Mobilization 3,530,395.00 0.00 6. Total Work Completed 38,968,374.97 7. Deductions -866.60 0.00 8. a.Contract Retentions -1,771,899.00 -24,974.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 37,195,609.37 474,506.77 10. Reduction Amt to Escrow 11. Payment to Escrow 1,771,890.00 12. Net Pymt. this Estimate 474,506.77