Dept. of Trans. PROGRESS Serial No. Contract No. 09-111-13-31 09-214614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 76% 09-INY-395-77.3/91.6 Federal Project: NONE Progress payment No. 18 Payment period ending: 04-20-09 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 925092405 Escrow No. 02348 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,280,120.81 816,230.80 2.a. Extra Work 358,811.78 43,706.10 b. Adjustment Comp. 944,422.93 -55,309.48 3. Materials on Hand 4. Earned Subject to Retention 19,583,355.52 804,627.42 5. Mobilization 2,100,000.00 0.00 6. Total Work Completed 21,683,355.52 7. Deductions 8. a.Contract Retentions -979,167.78 -40,231.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,704,187.74 764,396.05 10. Reduction Amt to Escrow 11. Payment to Escrow 979,160.00 12. Net Pymt. this Estimate 764,396.05