Dept. of Trans. PROGRESS Serial No. Contract No. 09-141-14-44 09-214614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 82% 09-INY-395-77.3/91.6 Federal Project: NONE Progress payment No. 19 Payment period ending: 05-20-09 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 925092405 Escrow No. 02348 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,337,596.92 4,057,476.11 2.a. Extra Work 373,363.68 14,551.90 b. Adjustment Comp. 642,990.91 -301,432.02 3. Materials on Hand 4. Earned Subject to Retention 23,353,951.51 3,770,595.99 5. Mobilization 2,100,000.00 0.00 6. Total Work Completed 25,453,951.51 7. Deductions 8. a.Contract Retentions -1,167,697.58 -188,529.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,286,253.93 3,582,066.19 10. Reduction Amt to Escrow 11. Payment to Escrow 1,000,000.00 12. Net Pymt. this Estimate 3,582,066.19