Dept. of Trans. PROGRESS Serial No. Contract No. 12-293-10-20 09-237704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 97% 09-MNO-395-118.7/119.6 Federal Project: ACHS-NHP3(237) 95(237) Progress payment No. 06 Payment period ending: 10-20-12 DISNEY CONSTRUCTION INC 875 MAHLER ROAD SUITE 188 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,817,751.00 1,047,568.50 2.a. Extra Work 77,225.70 0.00 b. Adjustment Comp. 1,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,895,976.70 1,047,568.50 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 7,895,976.70 7. Deductions -21,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,874,976.70 1,037,568.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,037,568.50