Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-242-10-11 09-237704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 09-MNO-395-118.7/119.6 Federal Project: ACHS-NHP3(237) 95(237) Progress payment No. 12 Payment period ending: 08-13-13 DISNEY CONSTRUCTION INC 859 COWAN ROAD SUITE 3 BURLINGAME CA 94513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,277,775.15 55,000.00 2.a. Extra Work 161,381.43 750.00 b. Adjustment Comp. 39,039.65 -40,960.35 3. Materials on Hand 4. Earned Subject to Retention 10,478,196.23 14,789.65 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 11,478,196.23 7. Deductions -2,227,300.00 157,700.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,250,896.23 172,489.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 172,489.65