Dept. of Trans. FINAL Serial No. Contract No. 16-005-08-59 09-237704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-MNO-395-118.7/119.6 ACHS-NHP3(237) 95(237) Progress payment No. 018 Payment period ending: 08-13-13 DISNEY CONSTRUCTION INC 859 COWAN ROAD SUITE 3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,351,775.15 0.00 2. a. Extra Work 231,328.05 0.00 b. Adustment Comp. 3,373,092.81 2,982,100.00 3. Materials on Hand 4. Earned Subject to Retention 13,956,196.01 2,982,100.00 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 14,956,196.01 7. Deductions -161,100.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,795,096.01 2,982,100.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,982,100.00