Dept. of Trans. PROGRESS Serial No. Contract No. 09-265-13-22 09-280104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 100% 09-MNO-395-109.7/110.2 Federal Project: 09-MNO-395-114.5/114.9 NONE Progress payment No. 04 Payment period ending: 09-20-09 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 759,237.02 0.00 2.a. Extra Work 41,927.87 41,927.87 b. Adjustment Comp. 17,935.00 17,935.00 3. Materials on Hand 4. Earned Subject to Retention 819,099.89 59,862.87 5. Mobilization 85,000.00 0.00 6. Total Work Completed 904,099.89 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 904,099.89 59,862.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,862.87