Dept. of Trans. PROGRESS Serial No. Contract No. 02-233-14-07 09-284604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 52% 09-MNO-203-4.8/8.7 Federal Project: ACST-P203(9) P-P203(9) Progress payment No. 04 Payment period ending: 08-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,253,611.70 1,824,229.70 2.a. Extra Work b. Adjustment Comp. -6,859.96 -6,859.96 3. Materials on Hand 4. Earned Subject to Retention 3,246,751.74 1,817,369.74 5. Mobilization 361,809.00 18,090.45 6. Total Work Completed 3,608,560.74 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -162,337.59 -87,380.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,436,223.15 1,738,079.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,738,079.40