Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-334-11-00 09-295104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 09-MNO-158-5.4/5.7 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-21-06 A P ENGINEERING CORPORATION 1271 COLUMBIA AVENUE SUITE 10 RIVERSIDE CA 92507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 352,786.75 10,135.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 352,786.75 10,135.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 402,786.75 7. Deductions -26,245.63 36,321.75 8. a.Contract Retentions -17,132.59 0.00 b. Unsatisfactory Prog. 0.00 4,244.90 c. Reduction after 95% Comp. 17,132.59 17,132.59 9. Total pay to Contractor 376,541.12 67,834.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,834.24