Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-275-08-05 09-295504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 09-INY-395-R0.0/R8.6 Federal Project: ACNH-P395(206) Progress payment No. 09 Payment period ending: 09-22-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,308,346.80 250.00 2.a. Extra Work 143,703.76 91,000.00 b. Adjustment Comp. 236,467.78 -47,070.20 3. Materials on Hand 4. Earned Subject to Retention 8,688,518.34 44,179.80 5. Mobilization 675,208.00 0.00 6. Total Work Completed 9,363,726.34 7. Deductions -39,327.54 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,324,398.80 24,179.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,179.80