Dept. of Trans. PROGRESS Serial No. Contract No. 06-262-14-14 09-301404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 58% 09-INY-395-25.8/31.2 Federal Project: 09-INY-395-41.3/44.9 NONE Progress payment No. 04 Payment period ending: 09-20-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,399,663.44 0.00 2.a. Extra Work 9,162.53 9,162.53 b. Adjustment Comp. -46,266.32 -2,765.53 3. Materials on Hand 4. Earned Subject to Retention 3,362,559.65 6,397.00 5. Mobilization 6. Total Work Completed 3,362,559.65 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -168,127.98 -319.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,184,431.67 6,077.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,077.15