Dept. of Trans. PROGRESS Serial No. Contract No. 07-141-09-53 09-307004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 12% 09-MNO-108-0.0/15.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 05-20-07 CIMARRON INC 10424 CIMARRON TRAIL OAKDALE CA 95361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 77,285.75 77,285.75 2.a. Extra Work 7,803.59 7,803.59 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 85,089.34 85,089.34 5. Mobilization 11,250.00 11,250.00 6. Total Work Completed 96,339.34 7. Deductions 8. a.Contract Retentions -8,508.93 -8,508.93 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 87,830.41 87,830.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,830.41