Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-13-03 09-307904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 88% 09-MNO-5712 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-20-08 DEN BOER ENGINEERING AND CONSTRUCTION INC 72-152 NORTHSHORE ST THOUSAND PALMS, CA 92276 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 921,480.00 48,268.00 2.a. Extra Work 29,193.97 25,988.28 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 950,673.97 74,256.28 5. Mobilization 6. Total Work Completed 950,673.97 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -47,533.70 -3,712.82 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 903,140.27 80,543.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 80,543.46