Dept. of Trans. PROGRESS Serial No. Contract No. 10-323-10-06 09-310604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 79% 09-INY-5505 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-19-10 MOJAVE DESERT BANK C/O RE COM DEVELOPMENT COMPANY 1450 NORTH NORMA RIDGECREST CA 93514 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 787,494.24 239,929.05 2.a. Extra Work 15,441.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 802,935.24 239,929.05 5. Mobilization 6. Total Work Completed 802,935.24 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 802,935.24 239,929.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 239,929.05