Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-342-08-11 09-314504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 140% 09-INY-395-R17.9/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-20-09 BOWE CONTRACTORS INC 42424 N 4TH ST EAST LANCASTER CA 93535 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 518,236.49 0.00 2.a. Extra Work 16,028.00 16,028.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 534,264.49 16,028.00 5. Mobilization 6. Total Work Completed 534,264.49 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 533,264.49 16,028.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,028.00