Dept. of Trans. PROGRESS Serial No. Contract No. 08-325-13-21 09-317204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 93% 09-INY-5709 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-20-08 STEVENS CONSTRUCTION INC 530 WEST AVENUE L LANCASTER CA 93534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 608,580.00 122,958.00 2.a. Extra Work 12,326.00 12,326.00 b. Adjustment Comp. -1,300.00 -1,300.00 3. Materials on Hand 4. Earned Subject to Retention 619,606.00 133,984.00 5. Mobilization 6. Total Work Completed 619,606.00 7. Deductions 8. a.Contract Retentions -30,980.30 -6,699.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 588,625.70 127,284.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 127,284.80