Dept. of Trans. PROGRESS Serial No. Contract No. 06-144-07-43 09-317604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 20% 09-MNO-395-93.0/120.5 Federal Project: ACNH-P395(210) Progress payment No. 02 Payment period ending: 05-20-06 B E C CONSTRUCTION CO 1645 ESMERALDA AVENUE MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 234,555.00 142,153.00 2.a. Extra Work 9,134.38 9,134.38 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 243,689.38 151,287.38 5. Mobilization 225,000.00 225,000.00 6. Total Work Completed 468,689.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 468,689.38 376,287.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 376,287.38