Dept. of Trans. PROGRESS Serial No. Contract No. 07-295-08-24 09-317704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 73% 09-INY-395-90.9/99.2 Federal Project: 09-INY-395-100.8/113.0 NONE 09-MNO-395-0.0/6.8 Progress payment No. 04 Payment period ending: 10-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,281,874.99 1,458,123.66 2.a. Extra Work b. Adjustment Comp. -93,030.81 -93,030.81 3. Materials on Hand 4. Earned Subject to Retention 2,188,844.18 1,365,092.85 5. Mobilization 570,000.00 120,000.00 6. Total Work Completed 2,758,844.18 7. Deductions 8. a.Contract Retentions -129,543.19 -47,168.06 b. Unsatisfactory Prog. 0.00 0.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,629,300.99 1,437,924.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,437,924.80